Schedule Of The Building Process
- 59
Planning, preliminary brief
- New build library, with approximately 1000 study seats, with access to power and data, and 5000m of stock.
- 60
Architectural competition
- Single stage competitive tender following OJEU procurement process.
- 61
Period of project
- Autumn 2011 - May 2015
- 62
Opening of the construction work
- August 2013
- 63
Conclusion of the construction
- April 2015
- 64
Furnishing and moving the collections
- April 2015 - June 2015
- 65
Opening of the new building for public
- 27th May 2015