Schedule Of The Building Process

59 Planning, preliminary brief
July 2012
60 Architectural competition
July 2012 - December 2012
61 Period of project
Public market > Tender in December 2012
62 Opening of the construction work
April 2013: asbestos removal - September 2013: work begins
63 Conclusion of the construction
12 months
64 Furnishing and moving the collections
Summer 2014
65 Opening of the new building for public
September 23rd 2014