Schedule Of The Building Process
- 59
Planning, preliminary brief
- August 2003 - June 2009: 2 projets (2004-2005 and 2006-2009)
- 60
Architectural competition
- None, architects selected out of references
- 61
Period of project
- Thierry Algrin / Alain del Zotto
- 62
Opening of the construction work
- July, 5th 2010 (August, 16th 2010)
- 63
Conclusion of the construction
- foreseen: 26 to 28 months / in fact: 40 months (August 2010 - December 2013)
- 64
Furnishing and moving the collections
- BRUYNZEEL (shelves) ; SCHLAPPMOBEL (chairs, desks, shelves) ; YAMAKADO (tables) ; ARTEMIDE (light) ; RIVES et DICOSTANZO (movings)
- 65
Opening of the new building for public
- November, 15th 2013 (partial opening: November, 5th 2013)