Schedule Of The Building Process

59 Planning, preliminary brief
2004-2005
60 Architectural competition
2005
61 Period of project
10.09.08-30.06.09
62 Opening of the construction work
April 2009
63 Conclusion of the construction
2009-2012
64 Furnishing and moving the collections
5 August 2011-11 September 2011 (modern collections only: special collections moved in oct/nov 2011)
65 Opening of the new building for public
12 September 2011 (Official opening to take place in September 2012)